Coast Guard Station Waterway Dredging
Project Summary
Dredge out the mooring area at the coast guard station in Green Bay, WI while allowing the USCG’s to perform their daily activities. The project worked 24 hour 7 days a week the entire construction schedule to complete work within time frame required. Large amounts of spoils were hauled off-site by a fleet of dump trucks to approved disposal sites while dredging work was completed.
Project Summary
Dredge out the mooring area at the coast guard station in Green Bay, WI while allowing the USCG’s to perform their daily activities. The project worked 24 hour 7 days a week the entire construction schedule to complete work within time frame required. Large amounts of spoils were hauled off-site by a fleet of dump trucks to approved disposal sites while dredging work was completed.